CASE STUDY

Scheme: C41/Q16 St Andrews
In-Situ Process: 150mm ‘Regen Plus’

‘Low carbon treatment trialled in Scotland’

Authority: Fife Council
Client: Fife Council
Date: July 2021
Area: 13,142m2
Surface: Double Dressed (PMB) 10mm & 6mm with Lockchip Surface Sealer
CO2 Saving: 76 tonnes - Approx. 1800 tonnes of Tar bound material encapsulated

St Andrews in Fife, Scotland is the home of golf and a picturesque coastal town which annually attracts large volumes of tourist traffic, especially when a major tournament is being held there. The C41 is used as one of the routes for leading traffic away from St Andrews at events so needed to be in such a condition to do so.

The local authority carried out a visual survey of the C41/Q16 route for patching and surface dressing and found that more than 65% of the road would need a min of 100mm deep asphalt inlay patching, this combined with the surface dressing of the entire section was deemed to be too expensive for the nature of the road and exceeded the budget for repairs.

Fife local authority contacted SPL to enquire whether we could offer an alternative solution to rehabilitate the failing road. Due to the nature of the road being relatively straight and free draining it was recommended the Regen Plus treatment would be a suitable choice for recycling the existing pavement.

This scheme was carried out using our latest generation Wirtgen 380CRi Downcut recycling machine and Paver in order to achieve higher outputs and increased level control. The improvement on levels and profiles over a patching option is very important in terms of reducing the dynamic loadings created by traffic on uneven surfaces thereby extending the roads life.
This layer was then covered with a double layer 10mm & 6mm surface dressing allowing the road to be trafficked under speed restrictions almost immediately.

Once the surface dressing was complete the whole area was brushed lightly before being sprayed with Bituchem’s “Lockchip” which is a sealed surface dressing system, the purpose of the system is to assist in minimising early life stone chipping loss.

This whole process of recycling, surface dressing and Lockchip was completed in 5 days allowing for a shorter road closure and minimising disruption to traffic.

Commercial benefits aside, this greatly reduced programme also leads to environmental benefits since the construction time is shortened assisting greatly with the Carbon targets and aspirations being set by central government and local authorities.

‘Regen Plus’ consists of pulverising and remixing the existing asphalt to a maximum depth of 150mm with an added blended cement content of 2%.