CASE STUDY

Scheme: B1160 College Road, Wissington
In-Situ Process: Deep Recycling using Down Cut W380CRi CIR machine

‘Innovation leads the one pass foam, cement and low layer grid trials in Norfolk’

Authority: Norfolk County Council
Term Contractor: Tarmac
Date: June 2021
Area: 10,230m2
Surface: Recycled HBM & Foamed Asphalt laid onto geogrid
CO2 Saving: 206 Tonnes

Wissington in Norfolk is the site of British Sugar’s largest refinery in the UK, indeed the largest in Europe, and the local highway network certainly takes the strain. Sitting on peat and soft ground, alongside deep drainage ditches, the client required a deeper solution than simple asphalt patching.

The reconstruction of this section of College Road involved in situ recycling the existing carriageway materials using cementitious binder placed onto the road prior to mixing, to create a Hydraulic Bound Material as well as a section of Foamed Bitumen binder injected into the mixing chamber of the recycler to create Bituminous bound cold recycled material. The recycled layers in both sections received an Asphalt Binder course and an Asphalt Surface course.

In addition, stabilisation was to be enhanced mechanically using a polypropylene grid below the recycled platform. The grid installation and both the foamed and cementitious recycling was carried out trialling the unique “one pass” approach developed by Stabilised Pavements using the latest generation Wirtgen 380CRi Recycler adapted with a new Grid dispensing attachment.

The extent of the works is a little under 2km of the B1160, heading South from British Sugar’s Wissington Sugar Factory on College Road. Providing access and egress for lorries into and out of the factory in addition to agricultural use and local traffic between West Dereham, Southery and Methwold.

The road condition prior to intervention was cracked and undulating, largely recognised as a result of the underlying ground conditions consisting of black peat and variable moistures. The impact of the peat and moisture has meant the structural integrity of the carriageway above has been compromised and consequently limiting its ability to carry the levels of traffic using it.

The proposed design solution in line with TRL 611 involved reconstruction using an in-situ recycled foundation layer with a structural stiffness sufficient to provide a sound platform for an asphalt binder and surface layer collectively appropriate for the 7.1 Million Standard Axles capacity of the road.

Analysis of this proposal validates the capacity in theory; however, the impact of the sub-grade may be a detrimental influence on the outcome in the longer term. Therefore, the incorporation of a grid was considered a further enhancement to retain the roads performance and condition.

A polypropylene geogrid, incorporated into the reconstruction below the recycled layer and above the subgrade had been proposed, which historically would have meant excavation of the carriageway to lay the grid before covering and recycling.

SPL have now developed a pioneering “one pass” technique by using the Wirtgen 380CRi. As the recycling takes place, this state-of-the-art recycler exposes a section of subgrade below the material conveyor for a brief period, presenting the opportunity to roll out the grid before the recycled layer is placed back onto this grid in the road through the following paver.

This installation technique has minimal impact on the delivery of the recycling in terms of productivity yet benefits the construction by acting as a spring constraint preventing the development of micro cracks through crack recovery when loads are applied within the grid layer. This mitigation of the development of cracking preserves the structural benefits and life of the hydraulically and bitumen bound recycled layers therefore preserving the integrity as a supporting layer to the Asphalt above.

In addition to the successful trial of this installation technique, a trial section using Foamed Bitumen to create a Bituminous bound cold recycled material was also carried out as an alternative to the cementitious Hydraulically Bound Material. Creation of the product in Phase 2 of the works (B1160 East West) was achieved utilising the Wirtgen 380Cri, recycling the existing carriageway aggregate using bitumen with good foaming characteristics and additions of cement and Pulverised Fuel Ash (PFA). This section will be monitored closely to evaluate the impact of moisture and sub-grade to establish performance compared to the HBM

At SPL it is our firm belief that measuring and managing our environmental performance in turn gives rise to innovation and efficiencies that lead to real commercial benefits. With improved efficiency around the grid installation, the high outputs of the W380Cri and the re-engineering of existing carriageway aggregates comes inevitable Carbon benefits. Using the CO2 calculator for this scheme, which considers industry recognised embodied material Carbon numbers as well as variables around travel we can demonstrate a Carbon saving of more than 200 Tonnes over traditional construction techniques. 200 Tonnes of Carbon being the equivalent to Greenhouse Gas Emissions from an average car driving 525,000 miles.