Scheme: Norfolk Trials Low Carbon Cement Alternative
In-Situ Process: Regen

Norfolk cut the Carbon with cement free binder trial

Authority: Norfolk County Council
Term Contractor: Tarmac
Date: June 2023
Area: 8,872 m2
CO2 Saving: 141 Tonnes using CEM 2 / 161 Tonnes using H-EVA

The OPC in our blended cement binder used for recycling comes with a high embodied Carbon figure of around 604Kg.CO2eq/T. This is a result of its highly emissive production involving quarrying, transport, fossil fuel firing and grinding. On this site an alternative has been trialled – based on Ettringite technology.

Using alkaline activation H-EVA is a “Clinker Free” cement produced in France by Hoffman Green approximately 60km from Dover in their Dunkirk.

  • H-EVA cement has a mechanical strength of up to 60 MPa within 28 days.
  • H-EVA cement has a formulation that does not contain one gram of clinker and a carbon footprint divided by 5 compared to the traditional cement.
  • This cement comes in the form of a powder that can be stored in a silo and is perfectly compatible with existing manufacturing processes.
  • H-EVA is a cement intended for the market of mortar and coating formulators, building site concretes and road binders

As a trial, SPL and Norse Laboratories will be monitoring theH-EVA performance which will determine the longer-term use of the product across the UK as a low Carbon alternative toBlended Cement products containing OPC.

Our trial hole and coring analysis determined the material suitability as well as understanding the roads characteristics in terms of drainage and edge restraint. Our Ground Penetrating Radar Survey also provided information around services and apparatus which again provided confidence around the in situ works. 

 

Product   

Embodied Carbon (kg/tonne) 

Project Footprint (kg/tonne) 

Saving over traditional asphalt (kg/tonne) 

CEM 2 

604 

17.7 

41.7 

H-EVA 

272 

11.2 

48.1

Using Cem 2, our Carbon Footprint was at 56 tonnes, which, whilst representing a significant 141 tonne saving over a traditional asphalt alternative, amounted to 17.7kg.CO2eq/tonne.

The H-EVA embodied carbon at 272Kg.CO2eq/t, reduced our footprint further to 35 tonnes, saving tonne over a traditional asphalt approach and amounted to 11.2kg.CO2eq/tonne – a decrease of 43%.

Eau Brink Road in Wiggenhall near Kings Lynn was well suited for Stabilised Pavement’s Regen process due to suitable material within the road as well as appropriate levels of traffic.

As an alternative to formal reconstruction or extensive patch repairs, the recycling of the existing carriageway material with a surface dressing represents a cost appropriate approach to highways maintenance.

Recycling to a depth of 150mm, the existing road layers were pulverised, compacted and re-shaped before the introduction of a cementitious binder (CEM 2 – a blend of 70% OPC and 30% PFA). The binder was spread at 2% by volume before the 150mm layer was mixed through with the blended cement and water to create our hydraulically bound material (HBM) which was once again compacted and shaped to ensure consistent depth of construction.

The profiling of the HBM also allows the smoothing out of high and low points in the existing carriageway, which cannot always be achieved through patch repairs alone. There are several benefits to this re-shaping:

  • Road users experience a vastly improved ride quality.
  • Falls are created to allow water to be vacated from the running surface.
  • The removal of bumps and troughs reduces the impact of dynamic loadings thereby extending the durability and life of the road structure.

In addition to the physical benefits the process is certainly one of the more sustainable approaches available since the re-engineering of the existing road layers does not involve importing virgin aggregates as with traditional asphalt reconstruction.

The recycled content sits at approximately 98% of the materials used – this amounts to 3061 Tonnes of granular material which is kept on site and recycled rather than transported and either treated for re-use or replaced. In turn this vastly reduces associated lorry movements which will not only avoid wear and tear on the surrounding network but also potentially decrease traffic disruption since around 300 lorry movements have been avoided.

Finally, the outputs are impressive. The works were completed in 4 shifts and included the double dressing of 10 & 6mm stone. Less time on site, less disruption and lower costs resulting in Environmental and commercial successes.